中央分隔带排水(纵向及横向排水管)施工方案讲解

2022-04-25 来源:乌哈旅游
浙江正方交通建设有限公司机西高速公路JXZT-1标段 排水工程施工方案

目 录

一、编制依据 ············································································· 2 二、工程概况 ············································································· 2 三、施工方法和工作程序 ······························································ 2 1.中央分隔带 ········································································· 2 2.横向排水管施工工艺流程 ······················································· 3 3.纵向排水沟施工工艺流程 ······················································· 7 4.纵向集水槽施工工艺流程 ······················································ 11 四、资源配置计划 ······································································ 12 1、人员安排 ········································································· 12 2、材料要求 ········································································· 12 3、施工机械 ········································································· 15 五、质量保证措施 ······································································ 15 1、成立质量管理组织机构 ······················································· 15 2、建立健全质量保证体系 ······················································· 16 3、确保工程质量的措施 ·························································· 17 六、安全保证措施 ······································································ 19 七、环境保护措施 ······································································ 24

1

浙江正方交通建设有限公司机西高速公路JXZT-1标段 排水工程施工方案

排水工程施工方案

一、编制依据

1、《公路桥涵施工技术规范》(JTJ041-2000) 2、《公路工程集料试验规程》(JTJ085-2000) 3、《公路工程水泥砼试验规程》(JTJ053-94) 4、《普通砼配合比设计规程》(JTJ/T55-2000) 5、《公路工程质量检验评定标准》(JTG F80/1-2004) 二、工程概况

郑州机场至周口西华高速公路(一期)全长106.3公里,起点位于拟建商登高速公路上,通过枢纽互通与拟建商登高速相连,先后和兰南高速、永登高速相连,终点在周口市西北接商周高速公路。项目位于开封市尉氏县、许昌市鄢陵县及周口市扶沟县、西华县境内。工程按四车道高速公路标准设计,荷载等级为公路-Ⅰ级,设计速度120公里/小时,路基宽28米。

本标段为JXZT-1标段,土建起讫里程K25+600~K32+000,长度6.4km;路面起讫里程K25+600~K42+600,长度17km。

按设计,路面及中央分隔带的排水设施包括:中央分隔带施工、纵向排水沟、横向排水管、纵向集水槽等。

本合同段施工图纸、合同清单所包含纵向排水沟(5869m)及横穿路基的横向排水管(1273mΦ110mmUPVC横向排水管及962mΦ300mm双壁波纹排水管)施工。 三、施工方法和工作程序

中央分隔带的排水设施包括:设在左右幅路面基层之间的纵向排水沟,按设计图纸的桩号设集水井及横向排水管,以及横向排水管出口的排水设施。由纵向碎石排水沟、集水井和横向排水管组成。 1. 中央分隔带

1、中央分隔带施工步骤

中央分隔带排水设施的施工顺序与路面主体工程的施工程序相协调,为避免相互干扰甚至彼此冲突的待工、返工浪费。其施工步骤与要求如下:

(1)横向排水管施工在垫层施工前埋设,同时在排水管入口处缠裹土

2

浙江正方交通建设有限公司机西高速公路JXZT-1标段 排水工程施工方案

工布,防止堵塞。

(2)在沥青面层施工前进行中央分隔带填土施工。

(3)在铺完一段上基层,并经质量检测合格后,随即施工纵向排水沟,排水沟挖完后将沟底面及两侧沟壁的松散砂石清扫干净,铺设两布一膜防渗土工布后回填米石,铺设透水土工布,敷设硅芯管后回填土。

(4)施工注意事项如下:

1)开挖管沟前测定其位置,经质检负责人和监理工程师检查确认。管沟要清扫干净(包括沟壁的松动碎石)后安放排水管。

2)排水管的接头事先用要求的材料密封,防止漏水。管道周围的混凝土必须捣实。

3)纵向渗沟两侧的上、下基层边缘的松散石子应清除干净,用砂浆抹平(注意先将基面洒水润湿),使纵向渗沟底面平顺,不致积水。

4)横向排水管安装时根据具体情况可适当调整其位置。如凹形竖曲线的底部必须设排水管并加密(上、下坡段长时);下坡段的桥头(搭板以外)、分隔带开口以及入孔处必须设置。此外,在无不利情况下,排水管对准已施工的边坡泄水槽设置。

5)回填排水沟砂砾时,注意防止损坏排水管道和放水层。 6)土工布的接头处必须粘接密实。 2、施工中重点控制的部位

(1)管道的埋设位置要适当;埋管混凝土的质量必须符合要求。 (2)排水沟与排水管的联接是否畅通而不渗漏。

(3)土工布铺设平整,接头粘结密封,两边的宽度达到要求。 (4)分层回填中央分隔带回填土。 2.横向排水管施工工艺流程

路基交验→施工放样→开挖沟槽→基底处理→拌制C20砼混凝土→回填C20 (砼基础浇筑) →夯实→安置横向排水管→再次回填C20砼→夯实→养生。

本合同段超高路段设置φ300mm的双壁波纹排水管,一般路段设置φ110mm的UPVC横向排水管。

3

浙江正方交通建设有限公司机西高速公路JXZT-1标段 排水工程施工方案

2.1排水施工工艺框图

测量放线 沟槽开挖 检查验收 基底处理 检查验收 基础浇筑 检查验收 管道安装 检查验收 回填浇筑 检查验收 养生

2.2测量放样

(1)根椐控制网放出主干管的中线,并在施工管段的起止端设置中桩,便于在施工过程中不断用经纬仪进行监控,保证管道的顺直。同时根据中线分别设置开挖边线、垫层、管座等的边桩,并利用边桩用水准仪分别标记沟底、垫层面、流水位等的高程。每一工序完成后应立即通线进行复测,及格后方可进入下一工序。

(2)用全站仪沿着主干管中线定出集水井的井心位置。再在井心依序放出开挖边线、垫层、基础、井身内壁边线,在各井旁设立施工水准点,并设立标志牌分别标记清楚各集水井的坑底、垫层、基础、收口、及井顶面高程,便于浇筑井身时使用。

(3)路肩边部横向排水管也利用全站仪及水准仪等进行施工监控,方法与主干管、井相同。

4

浙江正方交通建设有限公司机西高速公路JXZT-1标段 排水工程施工方案

(4)由于排水管位于不同的里程段。所以排水管、集水井施工前要复测上下标段及原有的流水位标高或测量控制点,根据管道坡度及长度进行推算结果与施工图相符后方可施工,否则应立即知会设计人及监理工程师。

(5)在挖沟槽见底前及浇注混凝土底板前,在管道铺设前,均应复测管道中心线及渗井、纵向排水等结构物的高程。 2.3沟槽开挖施工

(1)横向排水管严格按照图纸设计要求进行开挖。一般路段设置φ110mm的UPVC横向排水管,沟槽开挖距路床顶深28.5cm,宽25cm;超高路段设置φ300mm的双壁波纹管横向排水管,沟槽开挖距路床顶深34cm,宽30cm。

(2)沟槽开挖用风镐进行。沟槽开挖土方用自卸车外运至指定地点弃土。在开挖前,沟槽的断面,开挖的次序和堆土的位置由现场施工员向司机及土方工详细交底。在开挖过程中管理人员在现场指挥并经常检查沟槽的净空尺寸和中心位置,确保沟槽中心偏移符合规范要求。开挖过后要及时进行管道安装及出土处理,做好安全防范措施、减少意外事故。

(3)沟槽开挖的宽度按路面图纸设计宽度进行开挖。

(4)开挖时,随时测量监控,保证开挖的尺寸,轴线、沟槽底的高程达到设计图纸及沟槽验收规定的要求。 2.4沟槽检查验收

沟槽开挖完成后,进行检查验收。检查项目包括开挖断面、槽底标高、轴线位置、沟槽边坡等。沟槽开挖允许偏差和检查方法见表1 表1 沟槽开挖允许偏差和检查方法 序号 1 2 3 项 目 槽底高程 槽底中线每侧宽度 沟槽边坡 允许偏差 (mm) 0,-30 不小于规定 不陡于规定 检 查 频 率 范围 两 井 间 点数 3 6 6 检 查 方 法 用水准仪测量 挂中心线用尺量每侧3点 用坡度尺检验每侧计3点 2.5基底处理

沟槽开挖好后,清除基底的杂物和浮土,整平底基,必要进以振动夯进

5

浙江正方交通建设有限公司机西高速公路JXZT-1标段 排水工程施工方案

行振实。然后进行基础砼的浇筑、夯实并随时检测标高,合格后进行横向排水管道的敷设,最后继续浇筑砼直至与土基齐平。 2.6管道安装

(1)管道运输

管道由材料科统一采购并经检验合格后运至施工现场。具体注意以下几点:

1)管材在装卸、运输和堆放时应避免撞击,严禁抛摔。 2)管材成批运输时,需顺序堆放,应捆扎稳固。

3)管材应尽可能运至待安装管道的沟槽边,若施工场地条件不允许,可将管材集中堆放于指定场地,再二次转运。

4)严禁将管道放在尖锐的硬物上,短距离运输不得在坚硬不平地面和碎石面层上拖动或滚动。

5)管材堆放中应避免日光暴晒,并保持管间通风。堆放整齐不得受到扭曲损伤。

(2)管材检查

1)在运输前和货到现场后应对管道进行验收,检查厂商的生产许可证和质量合格证。

2)检查管道的内、外表面是否损坏,管材要求外观一致,管身不得有裂缝,管口不得有破损、裂口等缺陷。

3)管材端面应平整,与管中心轴线垂直。管材各项指标必须符合产品标准的规定。

4)管材耐压强度及刚度应满足设计要求。 5)管道的性能、尺寸应符合设计要求。 (3)管道铺设

1)管材敷设应由人工搬运,搬运时应轻抬轻放。

2)下管前,凡规定需进行管道变形检测的断面的管材,应预先量出该断面管道的实际直径,并做出记号。

3)下管采用人工搬运,严禁将管材由槽顶边滚入槽内。 4)安管时要控制好管底标高和坡度。

6

浙江正方交通建设有限公司机西高速公路JXZT-1标段 排水工程施工方案

5)管材应将插口顺水流方向、承口逆水流方向安装,安装应由下游往上游进行。 2.7管沟回填

横向排水管沟槽回填从管底向上浇筑砼与路基齐平,竖井底面及两侧以水泥砼现浇填筑。 2.8验收

施工完毕后,对沟槽管道施工过程中记录的试验、测量等资料整理成册报请监理工程师签收,合格后方可进入下道工序的施工。外观要求:集水管顶面不得高出相邻路面,集水管顺直,无折坡现象。

排水管及集水管检查项目 表2 项次 1 2 3 4 检 查 项 目 轴线偏离(mm) 沟、管底标高(mm) 基础宽、厚度(mm) 混凝土及砂浆强度(MPa) 规定值或允许偏差 50 ±20 不小于图纸规定 在合格标准之内 检 查 方 法 经纬仪或拉线:每两井间测3处 尺量:每两井间测3处 尺量:每两井间测3处 按JTJ F80/1-2004附录D、F检查

3.纵向排水沟施工工艺流程

基层施工完毕并检测合格→施工放样→开挖沟槽→基底清理→铺设两布一膜土工布→安置φ110mm打孔UPVC管→回填米石→铺设反虑土工布→敷设硅芯管→回填土。 3.1纵向排水沟施工工艺框图

7

浙江正方交通建设有限公司机西高速公路JXZT-1标段 排水工程施工方案

回填土 敷设硅芯管 检查验收 检查验收 铺设反虑土工布 回填米石 检查验收 安置φ110mm打孔UPVC管 检查验收 两布一膜土工布 检查验收 基底清理 检查验收 开挖沟槽 检查验收 施工放样 基层施工完毕并检测合格

3.2测量放样

(1)根椐控制网放出主干管的中线,并在施工管段的起止端设置中桩,便于在施工过程中不断用经纬仪进行监控,保证管道的顺直。同时根据中线

8

浙江正方交通建设有限公司机西高速公路JXZT-1标段 排水工程施工方案

分别设置开挖边线、垫层、管座等的边桩,并利用边桩用水准仪分别标记沟底、垫层面、流水位等的高程。每一工序完成后应立即通线进行复测,及格后方可进入下一工序。

(2)由于排水管位于不同的里程段。所以排水管、集水井施工前要复测上下标段及原有的流水位标高或测量控制点,根据管道坡度及长度进行推算结果与施工图相符后方可施工,否则应立即知会设计人及监理工程师。

(3)在挖沟槽见底前及浇注混凝土底板前,在管道铺设前,均应复测管道中心线及集水井、纵向排水沟等结构物的高程。 3.3沟槽开挖施工

(1)纵向排水沟严格按照图纸设计要求进行开挖。

(2)沟槽开挖用小型挖掘机配合风镐进行。沟槽开挖土方用自卸车外运至指定地点弃土。在开挖前,沟槽的断面,开挖的次序和堆土的位置由现场施工员向司机及土方工详细交底。在开挖过程中管理人员在现场指挥并经常检查沟槽的净空尺寸和中心位置,确保沟槽中心偏移符合规范要求。开挖过后及时进行管道安装及出土处理,做好安全防范措施、减少意外事故。

(3)沟槽开挖的宽度按路面图纸设计宽度进行开挖。

(4)开挖时,随时测量监控,保证开挖的尺寸,轴线、沟槽底的高程达到设计图纸及沟槽验收规定的要求。 3.4沟槽检查验收

沟槽开挖完成后,进行检查验收。检查项目包括开挖断面、槽底标高、轴线位置、沟槽边坡等。沟槽开挖允许偏差和检查方法见表1。 3.5基底处理

沟槽开挖好后,清除基底的杂物和浮土,整平底基,必要进以振动夯进行振实。并随时检测标高。合格后进行两布一膜土工布的铺设工作,要求把整个中分带断面铺满,并伸入每侧水稳15cm。 3.6管道安装

两布一膜土工布铺设完成后,进行φ100mm打孔排水管的敷设。 (1)管道运输

管道由材料科统一采购并经检验合格后运至施工现场。具体注意以下几

9

浙江正方交通建设有限公司机西高速公路JXZT-1标段 排水工程施工方案

点:

1)管材在装卸、运输和堆放时应避免撞击,严禁抛摔。 2)管材成批运输时,需顺序堆放,应捆扎稳固。

3)管材应尽可能运至待安装管道的沟槽边,若施工场地条件不允许,可将管材集中堆放于业主指定场地,再二次转运。

4)严禁将管道放在尖锐的硬物上,短距离运输不得在坚硬不平地面和碎石面层上拖动或滚动。

5)管材堆放中应避免日光暴晒,并保持管间通风。堆放整齐不得受到扭曲损伤。

(2)管材检查

1)在运输前和货到现场后应对管道进行验收,检查厂商的生产许可证和质量合格证。

2)检查管道的内、外表面是否损坏,管材要求外观一致,管身不得有裂缝,管口不得有破损、裂口等缺陷。

3)管材端面应平整,与管中心轴线垂直。管材各项指标必须符合产品标准的规定。

4)管材耐压强度及刚度应满足设计要求。 5)管道的性能、尺寸应符合设计要求。 (3)管道铺设

1)管材敷设应由人工搬运,搬运时应轻抬轻放。

2)下管前,凡规定需进行管道变形检测的断面的管材,应预先量出该断面管道的实际直径,并做出记号。

3)下管采用人工搬运,严禁将管材由槽顶边滚入槽内。 4)安管时要控制好管底标高和坡度。

5)管材应将插口顺水流方向、承口逆水流方向安装,安装应由下游往上游进行。

3.7管沟回填及铺设反虑土工布

纵向排水管(φ110mm打孔UPVC管)安装完毕后,随即回填米石。随时检测米石标高,直至达到设计要求。检测合格后在米石顶面铺设60cm

10

浙江正方交通建设有限公司机西高速公路JXZT-1标段 排水工程施工方案

宽反虑土工布,待敷设硅芯管后再分层回填土。 3.8验收

施工完毕后,对沟槽管道施工过程中记录的试验、测量等资料整理成册报请监理工程师签收,合格后方可进入下道工序的施工。 4.纵向集水槽施工工艺流程

基层交验→测量放样→集水槽底板砼浇注(预埋钢筋)→墙身模板立模→墙身C25砼浇注→养生→集水槽盖板安装。 4.1.测量放样

(1)根椐控制网放出纵向集水槽的中线,并在施工管段的起止端设置中桩,便于在施工过程中不断用全站仪进行监控,保证集水槽的顺直。同时根据利用边桩用水准仪分别标记集水槽沟底、集水槽顶面等的高程。每一工序完成后应立即通线进行复测,及格后方可进入下一工序。

(2)由于集水槽位于超高段。所以集水槽、集水井施工前要复测上下标段及原有的流水位标高或测量控制点,根据管道坡度及长度进行推算结果与施工图相符后方可施工,否则应立即知会设计人及监理工程师。 4.2.底板浇筑

施工前,把水稳层顶面清扫干净,随后绑扎墙身预埋钢筋,绑扎完毕后开始安装模板,底板的模板采用竹胶板,按照之前测量放样的点位和标高安装模板,模板安装完毕后报监理工程师检验后方可进行砼浇筑。 4.3.墙身立模

墙身模板采用60cm*150cm的平面钢模,外侧用钢筋和方木进行加固,保证集水槽墙身的外观。待监理工程师检查后方可进行砼浇筑,浇注时要严格控制顶面标高。 4.4.养生

墙身浇筑完毕后立即采用土工布进行覆盖养生,养生期不小于7天,待强度达到设计强度的85%后方可进行集水槽盖盖板的工作。 4.5.集水槽盖板安装

集水槽盖板安装之前确定集水槽墙身的强度达到设计要求的85%。安装前用1cm厚的砂浆将墙身顶面找平,并将集水槽内的垃圾和杂物清理干

11

浙江正方交通建设有限公司机西高速公路JXZT-1标段 排水工程施工方案

净后方可进行预制盖板的安装。安装时注意轻拿轻放,注意不要与集水槽墙身发生碰撞,以免造成预制盖板或者墙身砼发生损伤。 四、资源配置计划 1、人员安排

实行定岗、定员、制定出明确的岗位责任制,开工前进行人员培训,使每个人都明确本项目的工作任务、施工方法和质量标准,且制定本工序现场组织如下:

中央分隔带排水分项工程人员职责表

序号 1 2 3 4 5 6 7 8 姓名 赵卫华 叶伟杨 张旗 于洋 杜广志 徐龙军 吴吉浩 马浪 职 务 生产副经理 总工程师 测量工程师 技术主管 质检部长 试验室主任 物机部长 安全员

2、材料要求

1.中央分隔带回填土所用材料应符合图纸及下列要求。 通常情况下,下列材料为非适用性材料:

a.沼泽土、淤泥、泥碳、冻土、生活垃圾、建筑垃圾。 b.含有树根和易腐朽物质的土。 c.有机质含量大于5%的土。

d.液限大于50%、塑性指数大于26的土。

2.横向U PVC排水管、纵向打孔的U PVC排水管的质量应符合图纸及相关规范有关规定。中央分隔带排水设施所用材料技术要求:

12

职 责 负责全线排水工程施工 负责该分项工程方案的实施 负责该分项工程的测量工作 负责该分项工程技术工作 负责该分项工程的质量管理 负责该分项工程的试验检测 负责该分项工程的机械设备、材料管理及负责该分项工程的安全管理 浙江正方交通建设有限公司机西高速公路JXZT-1标段 排水工程施工方案

排水工程施工组织机构图

技术负责人 叶伟杨

合同计量部 排水工程施工队 测 量 队 张旗 施 工 员 彭玉祥 金晓辰 工程技术部 张广瑜 试 验 室 徐龙军 材 料 部 吴吉浩 财 务 科 梁涛 生产副经理:赵卫华 施工队长:刘东华 (1)Φ20cm硬聚氯乙烯U PVC管维卡软化温度≥80℃,纵向回缩率≤5%,落锤冲击试验≤5%,公称压力达1.0MPa,管材长度应由供需双方商定(偏差+0.4%~-0.2%),管材端头须切割平整,并与管材轴线垂直。

(2)U PVC双壁打孔波纹管的质量应符合图纸及下列要求。 直径ф117/110毫米的硬聚氯乙烯UPVC双壁打孔波纹管采用1米的管节进行扁平试验,当垂直方向加压至外径变形量为原外径的40%时,立即

13

浙江正方交通建设有限公司机西高速公路JXZT-1标段 排水工程施工方案

卸荷,试样不破坏、不分层;环刚度≥6.3kN/m2,纵向收缩率≤3%,透水率≥3.5%。

3.水泥混凝土应符合图纸和下列的要求。

(1)应由承包人进行配合比设计,并于混凝土浇筑或预制前35d完成,提交监理工程师审核批准,方可实施,强度应符合图纸的规定。

(2)配合比设计按《普通混凝土配合比设计规程》(JGJ 55-2000)通过计算、试配和调整确定。

4.水泥砂浆应符合图纸和下列的要求。

(1)砂浆等级应符合图纸的规定或监理工程师的要求。砂浆的强度等级系指70.7mm×70.7mm×70.7mm标准立方体试件,在温度20±3℃、相对湿度不小于90%的环境中养生28d,经抗压试验所得的极限抗压强度值,以MPa表示。

(2)砂浆所用的水泥、砂及水应符合第301节的规定。砂浆中宜用中砂或粗砂。

(3)水泥砂浆的配合比按《砌筑砂浆配合比设计规程》(JGJ 98-2000)的规定执行,强度满足图纸要求。

(4)除非监理工程师同意,不得用人工拌和砂浆。 5.横向排水沟水泥混凝土应符合图纸的要求。

6.隔渗层用防渗土工布应符合下列规定:机织丙纶防渗土工布采用二布一膜,重量为500克/平方米(其中布300克/平方米+膜200克/平方米),条带抗拉强度大于2450牛顿/5厘米,垂直向渗透系数小于1×10-13厘米/秒,搭接长度为15~20厘米。

7.渗沟顶面渗水土工布采用机织土工布滤布,机织土工滤布重量为150克/平方米,条带抗拉强度大于1800牛顿/5厘米,垂直向渗透系数大于0.029厘米/秒,搭接长度为50厘米。

8.水泥

水泥采用新乡同力P.C.42.5普通硅酸盐水泥。 9.水

水采用井水,洁净,不含有害物质。来自可疑水源的水应按相关规范要

14

浙江正方交通建设有限公司机西高速公路JXZT-1标段 排水工程施工方案

求进行试验,未经监理工程师批准的水源不得使用。 3、施工机械

提前对所用机械设备进行检修,确保所用机械以良好状态投入施工,所用主要设备有: 序号 1 2 3 4 5 6 7 8 9 设备名称 电焊机 钢筋切割机 钢筋弯曲机 混凝土罐车 挖掘机 振动压路机 自卸车 装载机 蛙式打夯机 规格型号 BX400-2 GS80 TJK-BC32 8m3 小松PC750-6 徐工 22T 北方奔驰3233k 厦工50 K100 数量 3 2 2 3 2 2 9 进场日期 2014.5 2014.5 2014.5 2013.7 2013.7 2013.7 2013.7 2013.7 2013.7 技术状况 良好 良好 良好 良好 良好 良好 良好 良好 良好 3 5 五、质量保证措施 1、成立质量管理组织机构

由项目经理和项目副经理、总工程师、质检人员参与组成的质量领导小组是本工程质量管理的最高领导机构,领导和组织实施、兑现本工程质量目标,见《质量管理组织机构框图》。

框图5.1 质量管理机构框图

15

浙江正方交通建设有限公司机西高速公路JXZT-1标段 排水工程施工方案

项目经理 项目副经理 总工程师 安全总监 物资设备部 工程部 安质部 工地试验室 1 2 3 4 5 2 3 4 5 1 1 2 3 4 5 1 2 3 4 5 成品、半成品质检入库、管理、发放地方大堆料源、装车质量监控机械设备检测、调试、维修、管理厂家生产许可证、产品质量检测报告按技术标准订货采购测量复核制制定专项施工技术措施,跟踪把关贯彻部颁规范,强化现场技术管理制定创优规划及季节性施工技术措施制定施工方案、工艺标准,进行技术交底复核设计文件,优化施工设计组贯按织彻部部颁标活颁动验准标进,行质分量项宣分传部教单育位工程验评QC 工序自检、监理工程师复验签证按设计文件和施工方案进行质量管理控制 重、难、新项目质量跟踪控制质量跟踪检测,数据分析整理,信息反馈土工、圬工各项工程试验 计量检查管理认证建材取样复验、抽验 项目部部门工作质量 各作业班组工序质量

2、建立健全质量保证体系

本项目将采用ISO9002国际质量体系和全面质量管理手段,严格控制施工质量,百分之百满足业主的要求。见《质量保证体系框图》。

16

浙江正方交通建设有限公司机西高速公路JXZT-1标段 排水工程施工方案

框图5.2 质量保证体系框图

质量第一 质 量 保 证 体 系 思想保证 组织保证 技术保证 施工保证 制度保证 提高质量意识 集团公司 质量管理部 贯彻ISO9002系列标准,推行全面质量管理 创优规划 经济法规 经济责任制 项目经理部质量管理领导小组 各项工作制度和标准 施工队质量小组 检查创优效果 制定创优措施 明确创优项目 TQC教育 用 户 务 服为下道工序是用户 制定教育计划 质量工作检查 现场QC小组活 动 岗前技术培训 熟悉图纸掌握规范 技 术 交 底 质 量 计 划 测 量 复 核 应用新技术工艺 优 质 优 价 完善计量支付手续 制定奖罚措施 签订承包保责任状 检查落实 技术岗位责任制 质量责任制 提高工作技能 提高工作技能 提高工作技能 接受业主和监理监督 定期不定期质量检查 进行自检互检交接检 利加用强现现代场化试检验测控手制段充分奖优罚劣 经济兑现

3、确保工程质量的措施

⑴质量方针与质量目标

17

质量评定 反 馈 实现质量目标 浙江正方交通建设有限公司机西高速公路JXZT-1标段 排水工程施工方案

坚持ISO9002质量体系的质量方针的质量目标,将此作为全体员工的自觉行动。

①质量方针

质量第一,精心施工,恪守合同,创精品工程。 ②质量目标

质量目标是:确保工程质量交工验收时全部达到《公路工程质量检验评定标准》的合格等级,竣工验收时工程质量等级达到优良,对重点工程或复杂工程争创国优或省优。保证做到:

a.工程一次验收合格率100%,优良品率必须大于95%以上; b.确保质量体系按GB/T19002-ISO9002的标准有效运行;

c.满足业主在工程合同中明确规定的各项要求,树立良好的社会信誉; d.对工程项目的基本质量终身负责。 ⑵做好质量策划工作

从工程一开始就做好质量策划,将所确定的质量目标层层分解到各质量部门,从管理、实施和检验把关三个层次和人员、设备、材料、工艺、环境五个方面采取一整套切实可行的措施,以确保工程质量。

①人员保证:安排得力的技术骨干,充实各关键技术岗位,选派专业理论强,且有丰富高速公路施工经验的人员,担任各部门负责人。各施工队和作业班组选派有丰富施工经验的人员负责。并结合本工程的特点和要求进一步开展岗前培训和技术交底;

②技术保证:施工前认真会审图纸,吃透设计意图,并组织人员对施工现场进行深入的踏勘和调查,制定切实可行的施工方案。努力推广和采用新技术、新工艺、新材料。建立二级测量复核制,由项目经理部测量班和各施工队测量员形成二级控制,坚持测量复核制度;

③原材料保证:施工所需主要原材料必须具有材料合格证和检验证,原材料进场须经收料员验收合格后方可进场,试验室不定期抽检,不合格材料应清除出场。入库原材料严格按仓库规定实施管理,严把质量关,对统供原材料、构件也不免除质量检验的责任;原材料检测。

18

浙江正方交通建设有限公司机西高速公路JXZT-1标段 排水工程施工方案

④设备保证:按工程性质调配所需的适用机械设备,坚持维修、保养制度,确保机械设备的完好,满足工程施工要求;

⑤环境保证:坚持经常性的天气预报监收,对不利天气及时采取相应措施,保证将自然灾害损失降到最低。加强与地方政府的关系协调,避免地方矛盾干扰工程施工。

⑶建立合格的试验室,严格抓好试验检测工作

①中心实验室选派技术能力强、经验丰富的人员负责,并配备一批工作责任心强的技术人员,充分发挥试验工作在质量把关中的关键作用;

②配备工程所需的各项试验设备(详见试验设备表),保证试验室具备技术规范所规定的各项试验能力,工地可临时配备一批必要的检测设备和材料试验的取样设备,以满足施工需要。各试验仪器设备均需按规定期限进行标定,保证试验成果的有效性;

③建立严格的试验室工作管理制度,严格按ISO9002质量管理体系来规范试验室管理工作。试验室由项目总工直接领导,试验人员要严格按技术规范进行试验,实事求是,严格把关,保证试验数据准确可靠。试验报告必须经试验室主任审签后,才能生效;

④每批进场建筑材料必须按规定抽样送试验室检验,严把进料质量关,工程成品和半成品必须按规范规定的抽样频率取样送检。

⑷认真贯彻执行各项技术规范

①各项工程的施工都必须严格遵循相应技术规范的规定,如实做好施工记录。各分项工程的施工负责人和各队质检员要严格控制、检查并承担责任;

②严格按图纸要求进行施工,按实际情况有必要变更设计的,必须遵守有关手续报经监理工程师批准,未经监理工程师同意,任何人无权擅改。 六、 安全保证措施 1.安全生产 1.1安全目标

1、杜绝重大伤亡。

2、无重大设备、火灾、管线、交通等事故。 3、事故负伤频率控制在0.6‰以下。

19

浙江正方交通建设有限公司机西高速公路JXZT-1标段 排水工程施工方案

4、安全管理规范,资料齐全,安全考核达业主要求。 1.2安全保证体系

(1)建立安全生产保证体系

“安全生产”是一切施工的前提条件,因此,在整个施工过程中,我们将始终贯彻“安全第一,预防为主”的方针,建立安全生产保证体系,见图6.1。

(2)健全安全组织,强化安全检查机构

成立以项目经理为组长,项目副经理、项目总工为副组长,各科室负责人为组员的安全领导小组,项目部设置专职安全员,各职能部门和各专业班组均设置兼职安全员,全面负责施工安全管理工作,责任到人,使安全工作上有专人抓,下有专人管,落到实处。确立明确的安全目标:坚持“安全第一,预防为主,教育开路,制度确保”的方针,坚决杜绝人为重大事故。

(3)贯彻GB/T28001:2001职业健康安全管理标准的管理体系文件,实施标准化管理,建立安全管理手册。 1.3安全保证措施

(1)建立安全保证制度

1)制定安全生产目标,实行单位连续安全生产天数累计奖励制和事故当事人与领导责任追究制,采用行政和经济相结合的奖罚办法,每月考核,月底兑现;

2)建立安全工作“日查月审”制度,安全工作要做到时时讲、处处讲,将“质量第一,安全第一”的口号叫响,使安全意识深入人心,不允许有半点侥幸麻痹的思想存在,安全员必须每日检查安全生产情况,发现并报告不安全因素和事故苗头,及时采取有效措施,杜绝不安全因素产生;

3)各专业作业班组都必须结合工程特点,补充制定完善的安全施工规章制度,报项目经理批准后认真贯彻执行。协作施工的人员必须遵守呼唤应答制和联络信号,确认安全后方可操作;

20

浙江正方交通建设有限公司机西高速公路JXZT-1标段 排水工程施工方案

图6.1 安全保证体系

防火、雷电、盗小组组长:张新塘

4)各种机械设备均由经考核合格的专职人员操作,严格执行操作规程,未经培训考核的无证人员严禁擅自操作。实行单机包机制,安全责任到人。加强运输管理,遵守交通规则,礼貌行车,服从当地交警部门的管理,防止交通事故发生。

5)在施工期间设置专人对施工机械进行管理,防止发生安全事故。 (2)施工机械的安全控制措施

1)各种机械操作人员和车辆驾驶员,必须取得操作合格证。对机械操作人员建立档案,专人管理。

21

安全领导小组组长:王荣全 安全小组组长:杜广志 专职安全员:马浪 执行小组组长 抢险小组组长 机料科 兼职安全员 吴吉浩 生产部 兼职安全员 刘东华 工程部 兼职安全员 张广瑜 杨宝君 彭玉祥 现场物资安全负责人 库存物资安全负责人 机械设备安全负责人 电气设备安全负责人 分项工程安全负责人 消防安全负责人 保安安全负责人 仇秀义 朱占法 姚童谢文权 王 于 丹 洋 闫纪云 浙江正方交通建设有限公司机西高速公路JXZT-1标段 排水工程施工方案

2)操作人员必须按照本机说明书规定,严格执行工作前的检查制度和工作中注意观察及工作后的检查保养制度。操作人员和指挥人员严格遵守安全操作技术规程,工作时集中思想,谨慎工作,不擅离职守,不酒后驾车。

3)驾驶室或操作室应保持整洁,严禁存放易燃、易爆物品,严禁酒后操作机械,严禁机械带病运转或超负荷运转。

4)严禁对运转中的机械设备进行维修、保养、调整等作业。 5)定期组织机电设备、车辆安全大检查,对检查中查出的安全问题,按照“三不放过”的原则进行调查处理,制定防范措施,防止机械事故的发生。严禁对运转中的机械设备进行维修、保养调整等作业。

6)施工车辆及碾压机具要安装蜂鸣器,防止在驾驶员视角盲区造成安全事故。

7)机械设备在施工现场停放时,应选择安全的停放地点,夜间应有专人看管。

(3)用电安全措施

1)施工现场制定详细的施工用电组织设计。生产用电已于当地电业局联系,采用当地现有电网就近接入施工场地,设置符合要求的配电室,配电室设置于地势高处,且高于地面1.5米以上,配电室周围设栅栏防护。按照当地电业局的要求布设低压办公用电及高压生产用电,高压电缆按照要求埋深50cm以上。

2) 施工现场的电气设备均符合建设部《施工现场临时用电安全技术规范》(JC46一S8)。执行 “一机、一闸、一箱”制。

3)变配电室符合“四防一遍”要求,建立相应的管理制度,配置好必要的安全防护用品。

4)电工作业时必须穿戴好个人防护用品,并严格执行电气安全操作规程,做到持证上岗。

5)专业电工持证上岗。临时用电工程的安装、维修和拆除,均由经过培训并取得上岗证的电工完成,非电工不准进行电工作业。

22

浙江正方交通建设有限公司机西高速公路JXZT-1标段 排水工程施工方案

6)建立电器安全管理和经济责任制度。项目配一名专职电器工程师负责电器采购、安装和安全工作。专职安全员负责巡视监督检查,专业电工负责施工现场电器安全。

7)施工现场装备行业统一规定的标准电源箱。电器线路和用电设备安装完成后,由专门管理部门验收合格后方可运行操作。场内架设的电力线路其悬挂高度及线距应符合安全规定。

8)室内配电盘、配电柜前要放绝缘垫,并安装漏电保护装置。种类电气开关和设备的金属外壳,均要设接地或接零保护。

9)移动的电气设备的供电线,应使用橡胶套电缆,穿过行车道时,应穿管方式埋地敷设,破损电缆不得使用。

10)经常对用电设备进行安全检查、测试, 每周一次测试漏电开关的接地电阻并有书面记录,发现问题,及时整改。

11)电工有权拒绝执行违反电器安全规范的工程指令,安全员有权制止违反用电安全的行为,严禁违章指挥和违章作业。

12)施工用电应急预案

①首先查明触电者是否脱离电源,并应防止触电者二次触电或抢救者触电。

②对触电者进行急救。

a.触电者停止呼吸,心脏不跳动,如果没有其他致命的外伤,应视触电为假死,必须立即在现场进行人工呼吸抢救,即使请医生和送医院途中也不能停止抢救。

b.抢救可用口对口、口对鼻人工呼吸法和胸外心脏挤压方法。

(4)安全生产检查制度

制订安全生产自查自纠办法,专职安全员日夜巡查,定期召开安全检查会议。

1.4加强安全教育和安全措施的设置

⑴所有工种操作人员都必须加强岗前培训,系统掌握有关安全知识,并通过考核合格后,持证上岗;

23

浙江正方交通建设有限公司机西高速公路JXZT-1标段 排水工程施工方案

⑵利用一切机会开展普遍的安全知识教育,提高职工对自然灾害知识的认识和在险情下的应对能力;

⑶所有进入陡坡、预制场等危险施工区的人员,都必须配带安全帽和安全通行证。

⑷项目部及施工处驻地设立保安人员,加强与当地公安部门的联系,共同维护好施工区域的治安管理;

⑸在施工作业现场及运输道路上,设置醒目的警示标志及各类操作规程和安全规则;

⑹实行安全生产交接制度,安全措施不落实或不安全、隐患不排除前,不得进入场地。

1.5加强安全工作的物质保障

⑴特殊环境下作业人员必须配发有关的劳动保护用品,如安全帽、安全带、防滑劳动鞋等;

⑵仓库及油库配备灭火器、消防沙等消防用具;

⑶定期对施工人员进行体检,对从事特殊条件下作业的人员要给予营养补助。 1.6其它保障

⑴加强天气预报的监收,随时掌握不利自然条件的影响,及时采取对策,防止因自然灾害的影响带来伤亡损失;

⑵办妥保险手续,除工程一切险及第三方责任险外,要对施工设备和人身安全投保。 七、环境保护措施

根据本项目的实际情况和业主对本项目施工的要求,适应修建环保型高速公路的潮流,本项目实施零污染、零破损措施,协调好与兄弟施工单位的关系,搞好交叉工程的施工,设专人保护好铺筑好的沥青层,保持沥青层的整洁,不得造成污染,严禁在沥青层上堆放施工产生的土或杂物,严禁在已铺沥青层上制作水泥砂浆,严禁漏油的施工车辆在沥青层上行驶。 同时也要保护好绿化、土建、防护设施等施工单位的劳动成果。 1.环境保护目标

24

浙江正方交通建设有限公司机西高速公路JXZT-1标段 排水工程施工方案

各种污染物排放水平满足国家和地方环境标准的要求,主要污染物排放水平较体系建立前有明显改善;改革施工工艺和材料,减少生产过程中对环境的污染;废弃物实分类管理,并实现废弃物的减量化、无害化和资源化;加强对能源使用的管理,合理利用能源,减少能源浪费;加强工程质量,控制各工序的废品率,减少废品损失。 2.环境保护保证体系

成立环境保护领导小组,项目经理任组长,综合办公室主任任副组长,各科室负责人为组员。负责项目施工过程中环境保护工作的宣传教育和具体环境保护措施的实施。

图7.1 环境保护领导小组机构框图

3.环境保护措施 (1)文物保护

1)施工中如发现文物古迹,要暂时停止作业,保护好现场,立即报告监理工程师,确保文物不流失;

2)需要借土、弃土时,对现有的或规划的保护文物遗址,采取避让的原则,另行进行地点的选择。

(2)防止水土流失和废料废方的处理

25

组长:项目经理 副组长:综合办公室主任 当地村(居)委会 监督员 当地环保部门 路面工程施工处 各职能部门 各生产班组 浙江正方交通建设有限公司机西高速公路JXZT-1标段 排水工程施工方案

1)在施工期间应始终保持工地的良好排水状态,与路基防护工程单位协调做好排水工作,各类临时排水渠道要与永久性排水设施相连接,不得引起淤积和冲刷;

2)驻地、施工便道、砂石料场、预制场周围挖好排水沟,确保占用的土地无冲刷,从本工程施工中开挖的土石材料对溪流和水道不产生淤积或堵塞,确保各种临时排水系统不改变现有水文状态;

3)未经监理工程师的事先书面同意,不破坏现有河道、水道、现有灌溉或排水系统的自然流动;

4)建立废旧物品回收、保留和处理制度,设废物收集箱,生活区设化粪池、污水沉淀池。对施工垃圾及生活垃圾有专人清理,并在指定地点处理。 (3)防止和减轻水、大气受污染

1)在设备选型时选择低污染设备,安装空气污染控制系统。 2)汽油等易挥发品的存放要密闭,并尽量缩短开启时间。

3)水泥混凝土、沥青混凝土、稳定土拌和站设有防尘措施。操作人员要配备必要的劳保防护用品。

4)施工废水、生活污水不得直接排入农田、耕地、灌溉渠和水库,不得排入饮用水源。施工现场与驻地要设置污水集水池,污水在集水池滤清后再排放;施工产生的废浆用专用汽车拉运至监理工程师指定的地点倾倒,并设渗坑进行处理,不得排放到河流、水沟、灌溉系统里,以免造成河流和水源污染。

5)施工区域、砂石料场在施工期间和完工以后要及时处理,减少对河道、溪流的侵蚀,防止沉渣进入河道和溪流;

6)冲洗含有沉积物的集料时,要设置沉淀池,做到达标排放; 7)施工期间,施工物料应堆放整齐,防止雨季或暴雨时,将物料随雨水径流排入地表及附近水域造成污染;

8)施工机械要防止严重漏油,禁止机械在运转中产生的油污水与维修施工机械时的油污水,未经处理就直接排放;

9)施工现场与施工机械经过的道路,要随时进行洒水抑尘;

26

浙江正方交通建设有限公司机西高速公路JXZT-1标段 排水工程施工方案

10)易于引起粉尘的细料或松散料要予以遮盖或适当洒水润湿,运输时用帆布或塑料盖套覆盖。运输水泥、砂、石、土等如有漏失,及时清扫干净,保持道路整洁。 (4)保护绿色植被

1)尽量保护公路用地范围以外的现有绿色植被,若因修建临时工程破坏了现有的绿色植被,应负责在拆除临时工程时予以恢复;

2)严格控制破坏植被的面积,除了不可避免的工程占地、砍伐以外,保证不发生其它形式的人为破坏;

3)保护好公路用地范围之外的古树名木和法定保护的树种,在公路用地范围之内的,要采取搬迁等措施加以保护。 (5)土地资源的保护

1)弃料要避免破坏或掩埋路基下侧的林木、农田及其它工程设施; 2)临时用地不再使用时,要根据业主及监理工程师的指令及时进行复耕、绿化;

3)借土要根据业主及监理工程师的指令到指定的场所取土,尽量不占耕地。当必须从耕地取土时,要将表层种植土,集中成堆保存。并在工程交工前做好还地工作;

4)自行组织采砂、采石时,要结合环保要求选择,在征得当地政府及环保管理部门的同意并办理必要的手续后方可采集;

5)对所有参入施工的人员进行加强保护自然资源及野生动植物的教育。 (6)完工后场地清理及恢复平整的环保措施

1)工程完工后对临时用地内所有建筑、生活垃圾应进行清理,垃圾运至指定位置处理,场地清理平整合格后,将其恢复原状。

2)施工完工后请当地政府有关部门进行环保验收,取得地方政府的认可,并从当地政府取得环保措施得到实施的证明材料,确保不留环保后患。

27