第8部分:配网工程
0.4kV低压硬(插接式)母线安装
作业指导书
编码:KGGAZ-04
KGGAZ-04 0.4kV 低压硬(插接式)母线安装作业指导书
目
次
1适用范围······················································································································································205 2编写依据······················································································································································205 3作业流程图··················································································································································205 4安全风险辨析与预控··································································································································205 5作业准备························································································································································13 6作业方法··························································································································································6 7质量控制措施及检验标准······························································································································9
241
中国南方电网有限责任公司电网建设施工作业指导书 第 8 部分:配网工程
1适用范围
1.1电压等级
0.4kV配网工程。
1.2电气类别低压硬(插接式)母线
的安装。
2编写依据
表2 编写依据
序号 1 2 3 引用资料名称 GB50254—1996《电气装置安装工程低压电器施工及验收规范》 GBJ149—1990《电气装置安装工程母线装置施工及验收规范》 GB50054—1995《低压配电设计规范》 4 DL/T5161.12—2002《电气装置安装工程质量检验及评定规程第12部分:低压电器施工质量检验》;DL/T5161.16—2002《电气装置安装工程质量检验及评定规程第16部分:1kV及以下配电线工程施工质量检验》;DL/T5161.4—2002《电气装置安装工程质量检验及评定规程第8部分:母线装置施工质量检验》 5
《中国南方电网有限责任公司基建工程质量控制作业标准(WHS)》
3作业流程图
图3 作业流程图
4安全风险辨析与预控
4.10.4kV低压硬(插接式)母线安装作业前,施工项目部根据该项目作业任务、施工条件,参照 《电网建设施工安全基准风险指南》(下简称《指南》)开展针对性安全风险评估工作,形成该任务的风险分析表。
4.2按《指南》中与0.4kV低压硬(插接式)母线安装作业相关联的《电网建设安全施工作业票》 (编码:KGGAZ-04-01/01),结合现场实际情况进行差异化分析,确定风险等级,现场技术员填写安全施工作业票,安全员审核,施工负责人签发。
242
KGGAZ-04 0.4kV 低压硬(插接式)母线安装作业指导书
4.3施工负责人核对风险控制措施,并在日站班会上对全体作业人员进行安全交底,接受交底的作业 人员负责将安全措施落实到各作业任务和步骤中。
4.4安全施工作业票由施工负责人现场持有,工作内容、地点不变时可连续使用10天,超过10天须重新办理作业票,在工作完成后上交项目部保存备查。
表4.1作业任务安全基准风险指南
序号 1 危害名称 切割时伤人 风险种类 割伤 风险等级 中等风险 风险控制措施 切割时,按规定配置防护措施 1.严格执行电焊作业规程; 2.严格执行持证上岗制度; 3.潮湿地方应使用绝缘垫; 4.正确使用个人安全防护用具; 5.电焊机外壳必须按规定接地 更换刃具,必须拉闸切断电源 2 电焊作业没有使用个人安全防护用具 灼(烫)伤触电 高风险 3 没有拉闸切断电源,更换刃具 触电割伤 中等风险
5作业准备
5.1作业前施工条件
表5.1作业前施工条件
序号 1 2 3 4 5 项目 任务单 图纸 预算材料表 施工方案 相关证照 内容 根据本单位实际设置内容(包含本项工作) 设计图纸 含主、辅材 施工组织、安全技术交底(项目部级) 根据需要办理涉及进入工作场所的手续、证件 确认人 本工序施工负责人 本工序施工负责人 本工序施工负责人 本工序施工负责人 本工序施工负责人 说明 经审批 经审批 经审批 经审批 有效 6 (1)确认变压器安装完成,经检验合格。 (2)确认0.4kV低压开关柜安装完成,经检验调试合格。 (3)检查配电房变压器与低压柜之间的空间满足低压硬 确认上一道工母线的吊装要求。 本工序施工负责人 序检查合格 (4)检查配电房楼面厚度、强度符合使用膨胀螺钉钻孔 要求。 (5)母线竖井安装,强电井须根据母线槽电流量大小留 有预留孔,有自由插拔馈电箱空间,且首层与顶楼孔洞同 心,强电井内应彻底清理干净,门锁齐备、有挡水墙 合格
5.2人员、主要工器具及仪器仪表配置
表5.2人员、主要工器具及仪器仪表配置
序号 项目 内容 施工阶段 建议工作人数 技术工人5+ 装卸工10 技术工人5+ 辅助工10 说明 现场施工质安员 1 人员配置 现场施工负责人 低压硬母线就位 低压硬母线安装 1 技术岗位必须持有与作业工种相应、有效的上岗证,辅助工不得从事电气设备安装等专业工作 1
243
中国南方电网有限责任公司电网建设施工作业指导书 第 8 部分:配网工程
2 施工内容低压硬(插接式)母线、软连接母线、吊装支架及相关配相对应的设备材料 件 检查确认设备材料符合设计要 求:①主、附件清单齐全;②硬 母线外观无损伤、变形;③产品 技术文件齐备,收集母线合格证 等原件资料及技术资料 3 工器具:手锤、活动扳手、套筒扳手、冲击钻、扭力扳手、 施工内容相对应的 梅花扳手、水平尺、梯子、搭建平台工具及安全工器具、绳 根据现场情况使用的工器具符器具、机械 索、对讲机等。 合相关要求 及工器具 机械:卷扬机、钢丝绳、手拉葫芦。仪表 仪表:电阻表(500~1000V) 4 完成开工程序 工作负责人向项目负责人报开工,并由项目负责人完成向监理单位开工报审手续 施工准备完成可报开工,当施 工准备不足时,上报项目负责人 协调解决
6作业方法
表6作业方法
序号 项目 内容 (1)现场施工负责人向进入本施工范围的所有工作人员明确 交待本次施工设备状态、作业内容、作业范围、进度要求、特 殊项目施工要求、作业标准、安全注意事项、危险点及控制措 施、危害环境的相应预防控制措施、人员分工,并签署(班组 级)安全技术交底表。 作业前工作 说明 1 按安规规定佩戴统一的安全帽,(2)工作负责人负责办理相关的工作许可手续,开工前做好统一佩戴有个人照片的作业证(或胸卡证),穿着统一的工作服 现场施工防护围蔽警示措施,夜间施工的,须有足够的照明。 (3)现场施工负责人组织检查确认进入本施工范围的所有工 作人员正确使用劳保用品和着装,并带领施工作业人员进入作业现场 现场施工负责人发出许可开工命令 2 启动作业 3 低压母线定位作业程序 (1)平置母线定位: 1)根据设计图纸及现场情况量度母线的长度、分段数量, 按要求加工分段母线成品。 2)核对图纸,确认母线型号、规格、数量及配套零配件符 合设计要求及与现场设备相配套。 3)分段检查母线标志是否清晰齐全,外观无损伤变形。 4)根据现场环境搭建施工平台,按设计图纸及设备定位后由工作负责人根据现场情况安预量度的尺寸进行支架定位。 排技术人员统一指挥母线支架定5)根据支架画线定位,安装母线吊装支架,支架安装直位 位、设备摆放,协调各配合人员之安排技术工人按规定程间距按设计要求,每单元段应确保两个吊架,在有插接箱、三 间的工作,序、规范要求进行装配,现场质安通、弯头等处要有支架吊桥。 员负责现场安全、质量监控 (2)竖井母线定位。 1)竖井母线固定支架保持中心在同一轴线。 2)将竖井的母线角铁支架装配好三边套上,所有螺栓均处于松解状态,将槽钢和弹簧、双头螺杆连接在支架上,弹簧处 于自动复位状态。 3)吊装母线卷扬机必须安装平稳,各滑轮安装牢固。 4)母线吊装时应拆除终端接口绝缘螺钉,使用专用螺杆,每段母线终端应套上保护盒,以免碰伤终端接口 由工作负责人根据现场情况安排技术人员统一指挥硬母线就位、1)硬母线及固定装置无尖角、毛刺,表面光洁平整,包括吊装进度,协调各配合人员之间的弯曲部分不应该有裂纹、皱褶、夹杂物及变形和扭曲现象。 调配,安排技术工人按规定程序、2)母线应由电源到负荷侧安装顺序,在变压器上方及低压 规范要求进行设备安装、调试,现质量监控 柜上进行柜面安装接线箱,变压器接线箱固定母线下垂部分超场质安员负责现场安全、过400mm加装拉杆吊架,保持母线的垂直度。 3)在变压器和低压柜上方或两侧施工时,应对变压器和低 (1)平置母线安装: 4 低压母线安装、设备连接作业程序 244
KGGAZ-04 0.4kV 低压硬(插接式)母线安装作业指导书
压柜进行保护,防止灰尘和砖碎进入柜体和损坏变压器。 4)安装用脚手架平台须安放平稳,枕木应捆扎牢固,不得使用腐朽、有明显裂痕的枕木。 5)使用手拉葫芦吊装时不能用钢丝绳或直接用葫芦挂链吊 装母线,须使用吊装带,吊装过程线槽下方不得站人。 6)使用梯子在变压器和低压柜上方、两侧安装母线时,应有专人扶持,不得碰损设备面板、仪表及操作按钮。 7)每段母线在拼装前须经现场绝缘测试合格,用毛刷清扫端头积尘,平衡吊装至桥架位置固定,双排母线吊装应同时进 行。 8)每两段母线须用水平尺调整至同一高度,端头插入时应保证绝缘板、绝缘膜完好无损,绝缘螺栓应上下错落双向对穿、紧固。 9)母线连接紧密,连接螺栓用力矩扳手紧固,紧固力矩符合如下表规定。
245
中国南方电网有限责任公司电网建设施工作业指导书 第 8 部分:配网工程
4 螺栓 力矩值 螺栓 力矩值 螺栓 力矩值 螺栓 力矩值 规格 N·m 规格 N·m 规格 N·m 规格 N·m M8 低压母线安装、设备连接作业程序 17.7~ 51.0~ 98.0~ 274.6~ M10 M14 M18 M24 22.6 60.8 127.4 343.2 10)母线安装后用中12镀锌圆钢或双色线可靠接地,圆钢弯曲 必须成圆角,接地线焊接时应对母线接口防护,防止意外损伤 母线壳体喷涂层。 (2)竖井母线安装: 1)安装时遵循由下向上的原则,绝缘测试后,将母线端口 用毛刷清理积尘; 2)使用专用吊装螺杆用卷扬机或手拉葫芦吊起待装母线缓 慢下放至指定位置支架上固定。 3)检查母线垂直度,插入绝缘螺栓并紧固,压紧垫片,检 查各绝缘插板无误后装上连接盖板,将角钢支架和弹簧、双头 螺杆连接在支架上,弹簧处于自动复位状态。 4)角钢安全嵌入母线固定支架内,紧固双头螺杆于角钢上, 锁紧上端点螺母,弹簧收缩距离根据母线槽规格(见表,依次 紧固支架固定螺栓及扣片螺栓)。 Ie 弹簧自长 弹簧根数 弹簧收缩 400A 100mm 2 10mm 630A 100mm 2 10mm 由工作负责人根据现场情况安 800A 100mm 2 11mm 排技术人员统一指挥硬母线就位、 吊装进度,协调各配合人员之间的1000A 100mm 2 12mm 调配,安排技术工人按规定程序、 1250A 100mm 2 13mm 规范要求进行设备安装、调试,现 场质安员负责现场安全、质量监控 1600A 100mm 2 13mm 2000A 100mm 4 10mm 2500A 100mm 4 10mm 注:此收缩为额定电流母线槽 3000mm 时收缩量。 8.8~ 31.4~ 78.5~ 156.9~ M12 M16 M20 10.8 39.2 98.1 196.2 5)调节双头螺杆下端点紧固角钢的螺母,直到角钢完全撑紧支架,使母线左右平衡且垂直,检查所有螺栓完全紧固无误后,缓慢松开母线的吊装绳。 6)一套母线安装完后,必须将弹簧上端的锁紧螺母完全松开,以保持裕度。 (3)设备连接: 1)变压器低压侧出线端与硬母线之间应用软母线连接,连接长度约30~50mm之间,软母线两端线夹表面光洁平整、镀银层完整。 2)软母线与电器接线端子连接时,不应使电器接线端子受到外加应力。 3)软母线不得有扭结、松股、断股或其他明显损伤、锈蚀 等现象,软连接厚度、数量必须满足变压器容量的过负荷电流。 4)软母线与电器接线连接后,裸露部分应加装绝缘护套和相序标色。 5)硬母线与低压柜进线端子之间按实际长度驳接硬母线,连接标准和过电流量符合设备容量的相关要求。 6)低压柜面进线端口必须安装防护铁箱,做好防止小动物 进入措施。 7)桥架本体及桥架各连接部位必须有可靠接地,接地体应满足设计要求 246
KGGAZ-04 0.4kV 低压硬(插接式)母线安装作业指导书
7质量控制措施及检验标准 7.1质量控制措施
7.1.1现场负责人应根据现场情况安排技术人员负责质量监控。
7.1.2作业人员必须熟悉工程作业流程和质量检验标准;技术岗位人员必须持有与作业相应、有效的上岗证。
7.1.3现场负责人在进行安全技术交底时必须详细介绍本作业质量控制要点、常见的质量通病及其防治措 施。
7.1.4作业现场必须有经审核批准的设计图纸和施工方案,作业人员必须按图施工。
7.1.5施工质量检验一般按以下方式进行。质量检验一般采用三级检验制,施工队(组)对所施工的分项 工程应进行100%的质量自检;项目部对所负责施工的分部工程和单位工程组织质量检查,复检比例不宜低于50%;公司对单位工程组织检查,抽检比例不宜低于20%。
7.1.6隐蔽工程施工完成以及全部工序作业完成(转序)时,必须提前24小时通知监理现场验收。
7.2检验标准
质量检验按《10kV~500kV输变电及配电工程质量验收与评定标准第8册:配网工程》中的Q/CSG表 8-7.8要求执行。
247
中国南方电网有限责任公司电网建设施工作业指导书 第 8 部分:配网工程
●附件1安全施工作业票
编码:KGGAZ-04-01/01
工作地点 技术员 现场安全员 现场负责人 工作时间 安全风险分析及控制措施 序号 危害名称 风险种类 风险等级 风险控制措施 1 切割时伤人 割伤 □中等风险 现场作业应严格执行相关安全规程及安全技术措施,并重点关注但不限于以下措施: 2 电焊作业无使用个人安全防护用具 灼(烫)伤、触电 □切割时,按规定配置防护措施。 □高风险 □严格执行电焊作业规程。 □严格执行持证上岗制度。 □潮湿地方应使用绝缘垫。 3 没有拉闸切断电源,更换刃具 触电、割伤 □正确使用个人安全防护用具。 □电焊机外壳必须按规定接地。 □中等风险 □必须拉闸切断电源更换刃具 安全补充事项/平面布置图 248
KGGAZ-04 0.4kV 低压硬(插接式)母线安装作业指导书
现场接受交底人员签名 备注 说明:(一)本票由现场技术员填写,现场安全员审核,现场负责人签发生效。现场负责人开工前核对风险控制措施 并宣读。(二)工作内容、地点、安全措施不变时本票最长可使用十天,否则应重新办票,用后上交备查;当人员发生变更时,应在备注栏记录变更情况。对新增人员进行交底,并签名确认。(三)应根据现场条件、范围和环境,补充安全事项或平面布置图。(四)当风险等级与基准风险等级不一致时,项目部应组织相关人员重新进行风险评估并制定措施。(五)基准风险等级与风险控制措施在开工前现场打“√”。(六)签名不齐全(含代签名的)均作废票处理。
249
因篇幅问题不能全部显示,请点此查看更多更全内容