您的当前位置:首页涵管工程工程量计算式

涵管工程工程量计算式

2022-11-15 来源:乌哈旅游
涵管工程浆砌石、砖墙工程量计算式

1. 桩号0+008.70

进水口浆砌石工程量:

(0.5+0.5+1.22*0.3)*1.22/2*2.31*2+(2.73+4.13)*2.2/2*0.4=6.87 出水口浆砌石工程量:

(0.5+0.5+1.6*0.3)*1.6/2*2.69*2+(2.96+4.3)*2.6/2*0.4+0.4*0.4*2 =10.47

小计浆砌石工程量:6.87+10.47=17.34 m3 进水口C20砼挡墙工程量

[(0.5+0.5+1.22*0.3)*1.22/2+1.27*0.4]*1.65-3.14*0.35*0.35*0.76 =1.92

出水口C20砼挡墙工程量

[(0.5+0.5+1.6*0.3)*1.6/2+1.38*0.4]*1.64-3.14*0.35*0.35*0.76 =2.55

小计C20砼工程量:1.92+2.55=4.47 m3

2. 桩号0+054.40

进水口浆砌石工程量:

(0.5+0.5+0.8*0.3)*0.8/2*2.22*2+(1.88+2.58)*2.2/2*0.4=4.16 出水口浆砌石工程量:

(0.5+0.5+1.5*0.3)*1.5/2*2.62*2+(2.7+3.3)*2.6/2*0.4+0.4*0.4*1 =8.98

小计:4.16+8.98=13.14 m3 进水口C20砼挡墙工程量

[(0.5+0.5+0.8*0.3)*0.8/2+1.2*0.4]*1.41-3.14*0.185*0.185*0.73 =1.30

出水口C20砼挡墙工程量

[(0.5+0.5+1.5*0.3)*1.5/2+1.51*0.4]*1.41-3.14*0.35*0.35*0.73 =2.10

小计C20砼工程量:1.30+2.10=3.40 m3

3. 桩号0+068.40

进水口浆砌石工程量:

(0.5+0.5+1.22*0.3)*1.22/2*2.31*2+(2.73+4.13)*2.2/2*0.4=6.87 出水口浆砌石工程量:

(0.5+0.5+1.6*0.3)*1.6/2*2.69*2+(2.96+4.3)*2.6/2*0.4+0.4*0.4*2 =10.47

小计浆砌石工程量:6.87+10.47=17.34 m3 进水口C20砼挡墙工程量

[(0.5+0.5+1.22*0.3)*1.22/2+1.27*0.4]*1.65-3.14*0.35*0.35*0.76 =1.92

出水口C20砼挡墙工程量

[(0.5+0.5+1.6*0.3)*1.6/2+1.38*0.4]*1.64-3.14*0.35*0.35*0.76 =2.55

小计C20砼工程量:1.92+2.55=4.47 m3

4. 桩号0+439.73

进水口浆砌石工程量:

(0.5+0.5+1*0.3)*1/2*2.22*2+(2.4+3.0)*2.2/2*0.4=5.26 出水口浆砌石工程量:

(0.5+0.5+2.03*0.3)*2.03/2*2.62*2+(3.02+3.62)*2.6/2*0.4+0.4*0.4*1 =12.17

小计浆砌石工程量:5.26+12.17=17.43 m3 进水口C20砼挡墙工程量

[(0.5+0.5+1*0.3)*1/2+1.2*0.4]*1.41-3.14*0.235*0.235*0.73=1.47 出水口C20砼挡墙工程量

[(0.5+0.5+2.03*0.3)*2.03/2+1.51*0.4]*1.41-3.14*0.235*0.235*0.73 =3.03

小计C20砼工程量:1.47+3.03=4.50 m3

5. 桩号0+615.44

进水口浆砌石工程量:

(0.5+0.5+1.45*0.3)*1.45/2*2.28*2+(3.07+4.27)*2.2/2*0.4=7.97 出水口浆砌石工程量:

(0.5+0.5+1.83*0.3)*1.83/2*2.67*2+(3.30+4.50)*2.6/2*0.4+0.4*0.4*2 =11.94

小计浆砌石工程量:7.97+11.94=19.91 m3 进水口C20砼挡墙工程量

[(0.5+0.5+1.45*0.3)*1.45/2+1.34*0.4]*1.84-3.14*0.465*0.465*0.79 =2.36

出水口C20砼挡墙工程量

[(0.5+0.5+1.83*0.3)*1.83/2+1.45*0.4]*1.83-3.14*0.465*0.0.465*0.79=3.60

小计C20砼工程量:2.36+3.60=5.96 m3

6. 桩号1+108

四沙井砌砖工程量:

(0.72*2+0.42*2)*0.12*0.5*4=0.55 m3

7. 桩号1+878.22

进水口浆砌石工程量:

(0.5+0.5+1.22*0.3)*1.22/2*2.31*2+(2.73+4.13)*2.2/2*0.4=6.87 出水口浆砌石工程量:

(0.5+0.5+1.6*0.3)*1.6/2*2.69*2+(2.96+4.3)*2.6/2*0.4+0.4*0.4*2 =10.47

小计浆砌石工程量:6.87+10.47=17.34 m3 进水口C20砼挡墙工程量

[(0.5+0.5+1.22*0.3)*1.22/2+1.27*0.4]*1.65-3.14*0.35*0.35*0.76 =1.92

出水口C20砼挡墙工程量

[(0.5+0.5+1.6*0.3)*1.6/2+1.38*0.4]*1.64-3.14*0.35*0.35*0.76 =2.55

小计C20砼工程量:1.92+2.55=4.47 m3

8. 桩号2+532.61

进水口浆砌石工程量:

(0.5+0.5+1*0.3)*1/2*2.22*2+(2.4+3.0)*2.2/2*0.4=5.26 出水口浆砌石工程量:

(0.5+0.5+2.03*0.3)*2.03/2*2.62*2+(3.02+3.62)*2.6/2*0.4+0.4*0.4*1 =12.17

小计浆砌石工程量:5.26+12.17=17.43 m3 进水口C20砼挡墙工程量

[(0.5+0.5+1*0.3)*1/2+1.2*0.4]*1.41-3.14*0.235*0.235*0.73=1.47 出水口C20砼挡墙工程量

[(0.5+0.5+2.03*0.3)*2.03/2+1.51*0.4]*1.41-3.14*0.235*0.235*0.73 =3.03

小计C20砼工程量:1.47+3.03=4.50 m3

9. 桩号3+006.07

进水口浆砌石工程量:

(0.5+0.5+1*0.3)*1/2*2.22*2+(2.4+3.0)*2.2/2*0.4=5.26 出水口浆砌石工程量:

(0.5+0.5+2.03*0.3)*2.03/2*2.62*2+(3.02+3.62)*2.6/2*0.4+0.4*0.4*1 =12.17

小计浆砌石工程量:5.26+12.17=17.43 m3 进水口C20砼挡墙工程量

[(0.5+0.5+1*0.3)*1/2+1.2*0.4]*1.41-3.14*0.235*0.235*0.73=1.47 出水口C20砼挡墙工程量

[(0.5+0.5+2.03*0.3)*2.03/2+1.51*0.4]*1.41-3.14*0.235*0.235*0.73 =3.03

小计C20砼工程量:1.47+3.03=4.50 m3

10. 排涝站进厂过路涵管 进水口砌砖工程量:

1.62*1.3*0.2+0.24*1.48*0.8*2+1.62*1.48*0.5-0.235*0.235*3.14*0.5 =2.10

出水口砌砖工程量:

1.62*1.3*0.2+0.24*1.93*0.8*2+1.14*0.4*0.24+1.62*1.93*0.5 -3.14*0.235*0.235*0.5=2.75 小计:2.10+2.75=4.85 m3

11. 桩号3+370

进水口砌砖工程量:

1.62*1.3*0.2+0.24*1.8*0.8*2+1.62*1.8*0.5-3.14*0.35*0.35*0.5=2.38

出水口砌砖工程量:

1.62*1.3*0.2+0.24*1.8*0.8*2+1.14*0.4*0.24+1.62*1.8*0.5 -3.14*0.35*0.35*0.5=2.49 小计:2.38+2.49=4.87 m3

12. 桩号3+372.49

进水口砌砖工程量:

1.62*1.3*0.2+0.24*1.23*0.8*2+1.62*1.23*0.5-3.14*0.35*0.35*0.5 =1.70

出水口砌砖工程量:

1.62*1.3*0.2+1.62*0.24*1.23+0.24*0.4*1.23+1.31*0.24*1.23*2 +0.37*0.62*1.23-3.14*0.35*0.35*0.24=1.98 小计:1.70+1.98=3.68 m3

涵管工程水泥砂浆抹面工程量计算式

1. 桩号0+008.70 平面砂浆抹面:

0.5*2.31*2+0.5*2.69*2+(0.6+2.0)*2.2/2*2+0.4*2=11.52 m2 立面砂浆抹面:

1.22*2.31*2+1.6*2.69*2+0.4*2*2+(0.5+0.5+1.22*0.3)*1.22/2*2 +4.13*0.4+(0.5+0.5+1.6*0.3)*1.6/2*2+4.3*0.4=23.25 m2

2. 桩号0+054.40 平面砂浆抹面:

0.5*2.22*2+0.5*2.62*2+(0.3+1.0)*2.2/2*2+0.4*1=8.10 m2 立面砂浆抹面:

0.8*2.22*2+1.5*2.62*2+0.4*1*2+(0.5+0.5+0.8*0.3)*0.8/2*2 +2.58*0.4+(0.5+0.5+1.5*0.3)*1.5/2*2+3.3*0.4=17.73 m2

3. 桩号0+068.40 平面砂浆抹面:

0.5*2.31*2+0.5*2.69*2+(0.6+2.0)*2.2/2*2+0.4*2=11.52 m2 立面砂浆抹面:

1.22*2.31*2+1.6*2.69*2+0.4*2*2+(0.5+0.5+1.22*0.3)*1.22/2*2 +4.13*0.4+(0.5+0.5+1.6*0.3)*1.6/2*2+4.3*0.4=23.25 m2

4. 桩号0+439.73 平面砂浆抹面:

0.5*2.22*2+0.5*2.62*2+(0.4+1.0)*2.2/2*2+0.4*1=8.32 m2 立面砂浆抹面:

1.0*2.22*2+2.03*2.62*2+0.4*1*2+(0.5+0.5+1.0*0.3)*1.0/2*2 +3.0*0.4+(0.5+0.5+2.03*0.3)*2.03/2*2+3.62*0.4=23.09 m2

5. 桩号0+615.44 平面砂浆抹面:

0.5*2.28*2+0.5*2.67*2+(0.8+2.0)*2.2/2*2+0.4*2=11.91 m2 立面砂浆抹面:

1.45*2.28*2+1.83*2.67*2+0.4*2*2+(0.5+0.5+1.45*0.3)*1.45/2*2 +4.27*0.4+(0.5+0.5+1.83*0.3)*1.83/2*2+4.50*0.4=26.41 m2

6. 桩号1+108

平面砂浆抹面:

(0.72*2+0.42*2)*0.12=0.27 m2 立面砂浆抹面:

(0.6*2+0.3*2)*0.5=0.9 m2

7. 桩号1+878.22 平面砂浆抹面:

0.5*2.31*2+0.5*2.69*2+(0.6+2.0)*2.2/2*2+0.4*2=11.52 m2 立面砂浆抹面:

1.22*2.31*2+1.6*2.69*2+0.4*2*2+(0.5+0.5+1.22*0.3)*1.22/2*2 +4.13*0.4+(0.5+0.5+1.6*0.3)*1.6/2*2+4.3*0.4=23.25 m2

8. 桩号2+532.61 平面砂浆抹面:

0.5*2.22*2+0.5*2.62*2+(0.4+1.0)*2.2/2*2+0.4*1=8.32 m2 立面砂浆抹面:

1.0*2.22*2+2.03*2.62*2+0.4*1*2+(0.5+0.5+1.0*0.3)*1.0/2*2 +3.0*0.4+(0.5+0.5+2.03*0.3)*2.03/2*2+3.62*0.4=23.09 m2

9. 桩号3+006.07 平面砂浆抹面:

0.5*2.22*2+0.5*2.62*2+(0.4+1.0)*2.2/2*2+0.4*1=8.32 m2 立面砂浆抹面:

1.0*2.22*2+2.03*2.62*2+0.4*1*2+(0.5+0.5+1.0*0.3)*1.0/2*2 +3.0*0.4+(0.5+0.5+2.03*0.3)*2.03/2*2+3.62*0.4=23.09 m2

10. 排涝站进厂过路涵管 平面砂浆抹面:

1.62*1.3*2=4.21 m2 立面砂浆抹面:

1.93*(0.8*2+1.14)+1.14*0.4*2+1.62*0.2+0.24*1.93*2 +1.48*(0.8*2+1.14)+1.62*0.2+1.48*0.24*2=12.54 m2

11. 桩号3+370 平面砂浆抹面:

1.62*1.3*2=4.21 m2 立面砂浆抹面:

1.8*(0.8*2+1.14)+1.14*0.4*2+1.62*0.2+0.24*1.8*2+1.8*(0.8*2+1.14)+1.62*0.2+1.8*0.24*2=13.15 m2

12. 桩号3+372.49 平面砂浆抹面:

1.62*1.3*2=4.21 m2 立面砂浆抹面:

1.62*0.24+0.24*0.4+1.31*0.24*2+0.37*0.62*0.24=1.98